Stars' End : version 4.0 : progess, west elevation

[ details | east | north | loft | garage | tree ]

[15 January 2000]

15 January 2000 -- loft stairs

[14 November 1999]

14 November 1999 -- kitchen floor

[17 October 1999]

17 October 1999 -- fake beams

[2 October 1999]

2 October 1999 -- scaffolding dropped

[18 September 1999]

18 September 1999 -- artexed

[11 September 1999]

11 September 1999 -- rendered and guttered

[21 August 1999]

21 August 1999 -- roof tiling (all but) finished

[13 August 1999]

13 August 1999 -- roof tiling restarts

[17 July 1999]

17 July 1999 -- chimney and final window

[10 July 1999]

10 July 1999 -- roofing starts

[3 July 1999]

3 July 1999 -- gables and windows

[19 June 1999]

19 June 1999 -- roof trusses

[12 June 1999]

12 June 1999 -- walls up to roof level

[5 June 1999]

5 June 1999 -- internal upper walls

[29 May 1999]

29 May 1999 -- some upper walls

[22 May 1999]

22 May 1999 -- first floor

[15 May 1999]

15 May 1999 -- higher walls

[8 May 1999]

8 May 1999 -- a little bit of scaffolding

[1 May 1999]

1 May 1999 -- most of the ground floor wall

[24 April 1999]

24 April 1999 -- our first wall

[17 April 1999]

17 April 1999 -- ground floor

[10 April 1999]

10 April 1999 -- 4 courses of bricks

[6 April 1999]

6 April 1999 -- groundbeams

[27 March1999]

27 March 1999 -- trenches

[14 Mar1999]

14 March 1999 -- piling finishes

[27 Feb 1999]

27 February 1999 -- piling starts

[15 Jan 1999]

15 January 1999 -- topsoil stripped

[20 Dec 1998]

20 December 1998 -- pre build