![[Stars' End]](2079.jpg)
Progress: [ west | east
| north | loft |
garage | tree ]
Soham: Oct 1999 -- ???
- 11 March 2001 -- The hearth ventilation grille
is fitted. This is the last internal item -- the interior is FINISHED!!
- 9 Jan 2001 -- The boarded loft felt a bit stuufy, so we had an
extra ventilation outlet added
- 1 January 2001 -- beginning of third millennium. 200th
anniversary of the discovery of the first asteroid, Ceres.
- now at 9280 books
- 30 December 2000 -- we fit mirrors in the
bathrooms
- 21 December 2000 -- winter solstice
- 7 October 2000 -- the bend in a piece of network conduit is fixed, by
installing a new socket. The lights
over the kitchen sink are installed. The final kitchen
wall tiling, around the cooker hood, is finished.
- 21 September 2000 -- vernal equinox
- 30 April 2000 -- the electric towel rail is
installed in the downstairs loo. Blanking plates are fixed over those
network conduit sockets currently unused
- 23 April 2000 -- the utility room cupboards (finally) get
their handles
- 16 April 2000 -- the downstairs loo floor is (mostly)
tiled.
- 9 April 2000 -- some door handles and door stops are attached.
- 2 April 2000 -- the loft stair doors are
stained.
- 27 February 2000 -- the kitchen splashbacks
are tiled, and progress is made on tiling the bathroom and the
hall floor.
- 20 February 2000 -- GRANITE -- the
kitchen worksurfaces and proper taps are
(finally!) installed, the new tiler tiles the en-suite
floor, the loft plasterboard is taped.
- 13 February 2000 -- the loft carpet is laid, and all our junk is now
up in the loft, instead of sitting on the landing
- 6 February 2000 -- a very small amount of bathroom tiling occurs, but
the tilers decide they do not want to do any more. The utility room
cupboard doors are hung.
- 30 January 2000 -- a small amount of bathroom tiling occurs. The
utility room cupboard walls and area around the loft staircase are
plastered.
- 23 January 2000 -- LOFT DOORS --
doors now cover the small
stairs up to the loft storage space.
- 15 January 2000 -- LOFT STAIRS -- the
small stairs up to the loft
storage space are installed. Work starts on the utility room
cupboards.
- 9 January 2000 -- BEAMS STAINED -- the
shower doors are installed, and a little more
bathroom tiling is done. The decking over the garage workshop is laid,
and the ceiling fitted underneath it. The fake
beams are stained dark brown.
- 2 January 2000 -- no building work happens this week (well, it is a
holiday!), but we do install the first part of the Ethernet.
- now at 9031 books
- 26 December 1999 -- LOFT BOARDED -- The
bathroom tiles are finally delivered, and some
are fixed. The side walls in the loft are
insulated and boarded. The secondary
loft ladder is fitted. We put up lots and
lots and lots and
lots and lots of
shelves.
- 21 December 1999 -- winter solstice
- 19 December 1999 -- The vent hole for the tumble drier is cut, and
the misplaced vent hole for the vacuum cleaner is filled. The final
consignment of furniture and books is delivered
from store. We put up lots and
lots of shelves.
- 12 December 1999 -- Some of the kitchen worktops have made their way
into the kitchen, but one piece is too small, and so nothing can be
fitted! The utility room splashbacks are tiled, and
the sink tap fitted. The final part of the loft insulation is
laid. The gas fire is connected. We put up lots
of shelves.
- 5 December 1999 -- The kitchen worktops are
delivered. The vacuum cleaner unit is fitted --
so now we can get rid of some of the plaster dust that's everywhere! The
second consignment of furniture and books is delivered from store. We
put up lots of shelves.
- 28 November 1999 -- DINING ROOM FLOOR -- The
drive is gravelled. The roof tilers finish their
work: the final ridge tiles on the garage, and
the slope on the chimney. The groundworks are
finished with a sophisticated overflow from the
rainwater tank. The dining room floor is fully laid,
sanded, and waxed, and there are enough boards left over to use as
matching skirting. The kitchen units have gained
their own skirting. Despite some work remaining,
we have some furniture and books delivered from store, and try to fit
old shelving to new walls.
- 21 November 1999 -- DRIVE --
PVCu bargeboards are fixed to the garage. The
drive hardcore is laid, so we are no longer
tramping sticky black mud into the house (building regs says the drive
has to incorporate a "double hammerhead", to be big enough to
allow a fire engine to turn!). Less mud means we can take up the
protective polythene from the floors, making the
house feel more like home. But until the kitchen and utility room are
complete -- we're still living out of the hall.
The dining room floor is about two thirds laid,
with sheets of ply laid over the polystyrene, then the
tongued-and-grooved floor boards stuck onto the ply.
- 14 November 1999 -- KITCHEN FLOOR -- The
kitchen gains a floor, and cupboard handles. The
utility room gains a shelf, a worktop and a sink,
but only temporary plumbing connections. The ventilation system is
connected up, with vent covers appearing in all the rooms (and a
special bonus exploratory hole in the landing
ceiling), pumping fresh air into the living rooms, and sucking stale air
out of the "wet "rooms, which means we can now close the
windows. The rainwater pump is plumbed in -- and
fires up every time we flush the loo -- and the
downpipes are fitted, to supply the tank. The vacuum
cleaner connections are fitted, but not yet the machine itself, so
we can't use it to clean up the grunge left from fitting them. The
decorators progress, with a first coat of stain on
the balustrading, which brings out the grain nicely. The gangplank
makes way for a front door step, making access a
little less exciting. The garage roller doors
are installed, although only the keyhole pads are visible
from the outside.
- 7 November 1999 -- GROUNDWORKS -- more
progress on the ground works, with tanks disappearing, and
oodles of manhole covers appearing (the foul
water system and rainwater recycling system converge at this point). The
sewage system pump is now connected, with its own fusebox
and control panel in the garage. Although the rainwater tank is
installed, the pump that allows the rainwater to
flush the loos is not yet, so the downpipes are
still not connected into the system. The dining
room floor has been delivered, and now the discussions start about
how to fit it. The kitchen progresses slowly: an
oven and hob, a sink, and some handleless cupboards (but no work
surfaces or flooring yet). Other essentials are installed:
the TV aerial, and the
telephone point. We even have our first
curtains up; so, although we still have to walk
the gangplank to get in, the house is nearly finished,
compared to the garage, anyway.
- 31 October 1999 -- MOVED IN -- the
hot water tank is fully plumbed in and the gas
is on, so we have hot water and underfloor heating (bliss!).
The sanitaryware and the sewage system are in
place, but the pump is not connected, so only shallow baths for now! (We
have a largish pumped holding tank, because the
sewer connection is slightly uphill). Plasterboarding
the loft has started. The fireplace is finally
complete (just waiting for the fire now...). The kitchen is not
yet finished, so all our white goods and stuff are in
the dining room for now. But at least we have the
essentials of life.
- 26 October 1999 -- we move in, to a very unfinished house
(electricity in places, and some cold water and drainage, but no
heating, no gas, no kitchen, no baths...)
- [25 October 1999 -- builder's September estimate of completion date]
- 24th October 1999 -- the electric fuse boxes
are all finished off, some sanitaryware has
appeared, the hot water tank is partly plumbed
in, the boiler is installed (but no gas to run
these, yet). The fireplace installers, who first appeared on the 18th
with an incorrect hearth, have returned, with an unmodified hearth, but
have managed to install some of it this time,
leaving the rest in kit form for now.
- 17th October 1999 -- FAKE BEAMS -- the
groundworks for the foul water system have
started, although there's still a lot of pipework
to be laid and inspection chambers to be fitted.
The electrician has started fitting the fuse boxes.
Not on the critical path, the fake beams are
attached to the render, and the staircase spindles
are being fixed. We have moved in a few essentials,
but are staying in B&Bs until the house is habitable!
- 15 October 1999 -- we move out of v3.1.
- 9 October 1999 -- the 4500 litre rainwater
recycling tank is on site -- but due to a scaffolding problem,
none of the groundworks that were to have been completed this week,
including the deep hole in which to bury the tank, have even been
started! Inside, the floating floors have been
laid over the polystyrene: chipboard in most rooms, and
two thicknesses of the more rigid Fermacell in
the rooms to be floor-tiled. Downstairs we have internal
doors, and in one room at least, skirting board. The
kitchen carcass has appeared.
- 2 October 1999 -- SCAFFOLDING DROPPED -- the
scaffolding has been (mostly) dropped,
letting us see the house properly for the first
time. The underfloor heating is now laid everywhere, adding the pipes
into the upstairs manifold and more pipes into
the master control panel. The chipboard
flooring gets laid directly on the polystyrene. (We had never
thought of polystyrene as a structural material, but now it forms our
floors as well as our foundations!) The
hot water tank has arrived, waiting to be
fitted. One of the advantages of building your own house is designing in
the little features -- like a drain under the
washing machine, in anticipation of those unfortunate overflows
(although it isn't yet going anywhere sophisticated).
- 25 September 1999 -- PLUMBING -- the
flooring has arrived, but so far is installed
only in the loft. The underfloor heating is
being laid: it comprises red plastic water piping
laid in polystyrene. The triple pipes run to
local small manifolds, which feed into the main
manifolds upstairs and downstairs,
and thence to the master control area. This
complexity makes the ordinary hot water plumbing
look relatively simple, and requires a lot of criss-cross
piping.
- 21 September 1999 -- vernal equinox
- 18 September 1999 -- ARTEXED -- the
front door is hung. Second fix electrics have
started, with a plethora of light switches, sockets, smoke
alarms, burglar alarm keypads and
detectors -- but it isn't
quite finished yet. Nearly all the ceilings are artexed
(it has a very peculiar smell). Floor boards are up
in the loft, if not yet fixed.
- [13 September 1999 -- builder's May estimate of completion date]
The Moon, along with Moonbase Alpha, is blasted out of Earth's
orbit.
- 11 September 1999 -- RENDERED AND GUTTERED --
second fix has started -- the carpenter has boxed in
the ventilation tubes, the plumber has started work on
the waste outlets, and the staircase is
continued round to edge the gallery. The outside
is partially rendered (the colour should lighten
up as it dries) and guttered. The
apples are getting past their best. And on the
way back from viewing, we spotted these his'n'hers
Tardises.
- 4 September 1999 -- plastering is now complete downstairs, too,
requiring cables to be hung up out of the way.
The impossible-to-photograph staircase is being installed. (Vertiginous
view from above -- below
front view from front door -- view from below
side of Dalek hiding place). The underside of the "porch"
has been weatherboarded in uPVC. [And finally...
spotted on an industrial estate whilst shopping
for sanitaryware -- where do they keep their stock?]
- 29 August 1999 -- ROOF TILING FINALLY FINISHED
-- roof tiling has finally finished with
the last bit above the front door done.
Plastering is complete upstairs, and just
starting downstairs, with the corners being done
first. Even with larger tile samples, it's hard
to judge what the bathroom will look like. The garage is making the
most visible progress. And the apple tree is
ripe for harvesting.
- 21 August 1999 -- ROOF TILING (ALL BUT) FINISHED
-- roof tiling has all but finished. The colour
of uPVC bargeboards, worry about which caused
all the delay, looks fine. The ventilation system is being installed,
with high vents in the outside walls,
outlet holes in the ceilings, and
shiny concertina tubes running up first floor
walls, from ground floor ceilings into the loft, where the
pump and heat exchanger resides. The vacuum
cleaner system, from the same supplier, has smaller
pipes and lower vents. The
staircase and front door
have been delivered, waiting for installation. The downstairs ceilings
are now completely plasterboarded too, and wet-plastering
the walls has just started, making the walls silky smooth to the
touch, but much less interesting to photograph. Outside,
the garage is beginning to take shape.
- 13 August 1999 -- ROOF TILING RESTARTS --
roof tiling has restarted, at long last! First
fix electrics are nearing completion: here we have
a double power socket, a TV point, conduit for computer cables, a
telephone point, and another double power socket. Life must have been
much simpler before electricity! The upstairs
ceilings are completely plasterboarded, but the downstairs
ones only partially, because first they had to rebate
the wiring. The garage's concrete slab floor
has been poured.
- 11 August 1999 -- total
eclipse of the sun
- 8 August 1999 -- and the tiles still aren't on the roof.
Inside, first fix electrical continues: there are there are
even more wires everywhere, some of which are now
properly conduited and boxed, and some of which
are ready for the outside lights.
- 31 July 1999 -- and the tiles still aren't on the roof -- apparently
there has been a delay with the bargeboards and soffits, but everything
is due Real Soon Now. Inside, first fix electrical has started: there
are wires everywhere, and we've added
our own hand-written notes to the electrician.
MDF windowsills are held in place with giant staples.
Lots of little holes have been drilled in the
exterior walls, to insulate the cavity with blown
fibre. And it's difficult to decide on tile colours when the
samples are so small.
- 24 July 1999 -- the tiles still aren't on the roof. There has been
some internal progress: "first fix" carpentry has started,
which means door frames, some battens
on the concrete ceiling, to attach the plasterboard to, and some
more battens crossing the rafters. The
liner and reinforcing mesh for the garage slab
are in place. But that's it for the week ... and they still
claim they will be finished on time ... which is now only seven weeks
away!
- 20 July 1999 -- 30 years on from that "One Small Step"
-- so when are we going to do it again??
- 17 July 1999 -- CHIMNEY AND FINAL WINDOW --
the chimney and the final bit
of the roof structure are finished. The roof and window
over the front door have been complicated enough,
both inside and out, to delay the roof tiling by
a week -- as have the rather complicated varieties of
ridge tiles. The roof steel beam is no longer supported on a
scrappy pieces of wood [as it was earlier on],
but on little pieces of something stronger. The
driveway is temporarily covered in strangely
patterned concrete, and work on the garage
has started in earnest.
- [mid July 1999 -- builder's January estimate of completion date,
before piling hiatus.]
- 10 July 1999 -- ROOFING STARTS --
roofing has started, with much battens, felt and
strange rafter vents, but the only tiling (with "pre-aged"
look tiles), so far is half of the back, with
other tiles poised ready to lay, which can be
seen only from the vertiginous top scaffolding. More cross pieces have
been added to the roof trusses, to strengthen the structure -- which
leads us to ask, what is holding these two halves of
the roof together? And the apple tree is in
fruit.
- 3 July 1999 -- GABLES AND WINDOWS -- the
gable ends are bricked in, showing us what the
ladder-like end roof pieces are for. The roof
tiles and ridge tiles are on site.
The windows are fitted -- all except
for the one that will go above the front door. But
the patio doors are wrong -- they should be all
glass. If we had had better 3-D imaginations, we would have
left the roof space open in this room -- we'll
have to remember that for the next one we build! Currently our staircase
is a little narrow. We get a great view
from roof level; looking back in the other
direction, we can just see the roof trusses through binoculars, but
not with the the camera zoomed to 50mm. (If this
was the movies, we could just magically zoom in with the computer and
see them; in real life all we get doing that is bigger
pixels.)
- 25 June 1999 -- we have received an offer for
Stars' End 3.1, so have told the builders
we are now holding them to their end date. Then ... nothing happened all
week!
- 21 June 1999 -- summer solstice
- 19 June 1999 -- ROOF TRUSSES -- the
roof trusses are in place. The last piece of
steel, part of the roof support, is in place, but is itself
not that well supported yet. That open attic roof
trusses will give us space in the main loft. The
other parts of the roof are more complex shapes.
The "wall plate", significant as a stage in the mortgage,
appears to be this scrappy piece of timber
screwed to the top of the wall. We can now see the shape
of the whole house from the front.
- 12 June 1999 -- WALLS UP TO ROOF LEVEL --
a third course of scaffolding takes the
brickwork up to roof level. The builders decided
they didn't like the lintels over some internal doors [as
they were originally], so have replaced them
with a much stronger beam. From the
front, it's even beginning to look like the
drawings.
- 5 June 1999 -- INTERNAL UPPER WALLS --
more scaffolding is in place, ready for the
outer brickwork. It is covered with piles of bricks,
which hide the fact that inner walls have
appeared upstairs. All this blockwork should
give better sound insulation and bookcase supports than flimsy
plasterboard.
- 29 May 1999 -- SOME UPPER WALLS -- the
walls grow some more, with the now-completed
concrete first floor being used to support as yet
only potential upper walls (and how did we get up there to
photograph it when there is no staircase yet?).
The brick soldier course at first floor level
provides subtle relief from the mass of brickwork. The
roof trusses are already on site, if not on
the house yet. Progress might look good, but not much has happened to
the garage since early April, beyond a crop of
buttercups.
- 22 May 1999 -- FIRST FLOOR -- our vantage
point is not high enough to show the concrete first
floor nearly completed, but the view from below shows
the beams and blocks over our heads.
Big steel lintels run across the corbels to
support the overhang, and more steelwork
supports the landing floor. With the ceiling blocking out the sky, the
downstairs begins to take shape with rooms, not
just walls.
- 15 May 1999 -- HIGHER WALLS -- the
walls grow higher, up to the level of the
corbelling (which supports the first floor
overhang), and interior walls appear, too. The
hall brickwork is nearly finished. No lo-tech
carrying of hods up ladders nowadays: a forklift lifts the pallets up to
a hi-rise platform. The pre-made
insulated lintels look quite hi-tech, too.
- 8 May 1999 -- A LITTLE BIT OF SCAFFOLDING --
nothing more has happened except a little bit of
scaffolding appearing. The builders must be concerned about
progress, too, because they are working on a
Saturday. This corner to corner view
won't be possible once the interior walls are in place.
- 1 May 1999 -- MOST OF THE GROUD FLOOR WALL --
much of the ground floor cavity wall is in
place, a few courses higher than last week around the
kitchen window and dining room doors. The front door takes shape,
from the outside and from the
inside, with interior brickwork. The fireplace
is a hole in the wall, and we won't get this view
up the chimney again. There seems to have
been a small accident with a palette of bricks.
- 27 March 1999 -- TRENCHES --
the garage trenches are dug. All the trench
bottoms have a skim of concrete, and the piles are
cut off to a level, leaving strange
cylindrical spoil, like fossilised dragon droppings, where the
piles had been filled with too much concrete. Birds
have been having fun in the drying concrete.
- 22 March 1999 -- trenches to hold the concrete
groundbeams are dug: it's beginning to look like real foundations
now, although not all the water problems have
been solved! Hand-crafted steel lattice work
are to provide reinforcement in the groundbeams between the piles.
- 21 Mar 1999 -- spring equinox
- 14 Mar 1999 -- PILING FINISHES -- all of
February's yellow circles have become driven piles,
no longer hollow, but filled with reinforcing
steel and concrete. And one day, this pile
of topsoil will be our garden.
- 6 Mar 1999 -- 16 more piles piled. Our plot has awkward access, and
the builders had expressed concern that they might not be able to get
their piling rig on site. So we were expecting some massive, lumbering
juggernaut, not a cute little escapee from the SF
film Short Circuit. ("Number Five is Alive" and well,
and driving piles in Soham?)
- 27 February 1999 -- PILING STARTS -- spring
has sprung, as have piles of piles, 15 of which
hollow steel tubes are driven deep in the
ground.
- 20 February 1999 -- Piling is due to start soon: 29 9"x5m piles
(doncha just love metric units?) for the house, and 12 6"x5m piles
for the garage, are to be driven over the next three weeks. But at the
moment all we have are some yellow circles.
- 11 February 1999 -- Neptune: furthest planet from the sun, 1979
-- 1999. After its 20 year foray inside the orbit of its neighbour,
today Pluto once again regains its title of outermost planet of the
Solar System.
- 27 January 1999 -- The architect, the builder, and the structural
engineer dig a second hole: the building regulations inspector says it's
nice stiff clay, and we don't need to go deeper than 2m after all. But
this hole rapidly fills with water, too. And so we need to stop thinking
trench-fill foundations, and start thinking pilings. Both holes are
filled in again, while a new design is drawn up...
- 14 January 1999 -- TOPSOIL STRIPPED -- ...
and then stops almost straight away: the building regulations inspector
worries that the surrounding conifers will leach
all the water out of the ground, and that we
might need 3m deep foundations, rather than the planned 2m ones.
- 11 January 1999 -- Work starts on the building
site, by stripping off the topsoil ...
- now at 8798 books
- December 1998 -- PRE-BUILD --
The plot just before work begins
- December 1998 -- we find our builder
- Royal Greenwich Observatory, 1675--1998. R.I.P.
- Spring/Summer/Autumn 1998 -- we search hard for another builder...
- April 1998 -- after a slight hiccup over sewer access is fixed, we
finally buy the plot. But by now our builder has evaporated.
- 21 March 1998 -- we visit the Home Building and Renovating Show
at Birmingham NEC, and find our roof tiles
- 5 March 1998 -- East Cambridgeshire District Council grants planning
permission
- Jan 1998 -- now at 8560 books
- November 1997 -- we apply for planning permission
- November 1997 -- the vendors accept our second, de-loomed,
Tudor-bethan house design
- October 1997 -- the vendors reject our first
proposed design as too "looming"
- October 1997 -- we identify a suitable builder
- 20 September 1997 -- we visit the Self Build Homes Show at
Alexandra Palace, to get our momentum going again, and get some detailed
ideas
- 9 September 1997 -- we make an offer for a quarter of an acre in
Soham, subject to planning approval, both from the Council, and from the
vendors (who are to be our neighbours)
- much of 1997 -- we continue searching for a plot, visiting lots of
patches of scrubby grass, and a few old barns
- Jan 1997 -- now at 8225 books
- October 1996 -- we make an offer for a lovely plot in Balsham, at
which point the vendors withdraw it from the market. Apparently they
were simply trying to find out how much it was worth. Grrrr.
- 1996 -- we decide to "self-build", and start searching for
a suitable plot
- As our story "progresses", we include the odd
astronomical event in our log, to give a feel for the similar kind of
timescales involved.
Earlier Stars' Ends